(This diary is an aggregation of the individual project diaries.)
Group Number and Group Name |
Project Description |
Individual(s) Preparing |
Preparation Date |
Review Date |
PMO |
Project Firestorm |
James Xu |
2/11/11 |
4/1/11 |
Task or subtask |
Assigned to |
Date |
Hours scheduled |
Hours accumulated |
Percent completed |
What’s going well? What’s not going well? Additional resources (people, technology) required? Are users and management participating? |
---|---|---|---|---|---|---|
Requirements gathered |
James Xu |
2/16/11 |
40 |
32 |
100 |
|
Team development and project planning |
James Xu |
2/16/11 |
8 |
8 |
100 |
|
Legal plans |
Norma Gleeson |
3/3/11 |
240 |
240 |
100 |
|
R&D plans |
Garry Hall |
3/10/11 |
480 |
540 |
100 |
Over budget due to expanded scope. |
Accounting plans |
Michel Bulan |
3/24/11 |
240 |
240 |
100 |
On budget and on plan. |
HR plans |
Davis Wilson |
3/31/11 |
440 |
420 |
100 |
Completed under budget and ahead of plan. |
Funding and investments |
Norma Gleeson |
5/5/11 |
480 |
240 |
50 |
|
Employee recruitment |
Davis Wilson |
6/23/11 |
480 |
0 |
0 |
|
Employee contracts |
Davis Wilson |
7/7/11 |
80 |
0 |
0 |
|
Development |
Garry Hall |
11/10/11 |
960 |
0 |
0 |
|
IP (patents) |
Norma Gleeson |
11/10/11 |
730 |
0 |
0 |