Consequential Damages

15 January, 2016 - 09:33

EBWS, LLC v. Britly Corp.

928 A.2d 497 (Vt. 2007)

Reiber, C.J.

The Ransom family owns Rock Bottom Farm in Strafford, Vermont, where Earl Ransom owns a dairy herd and operates an organic dairy farm. In 2000, the Ransoms decided to build a creamery on-site to process their milk and formed EBWS, LLC to operate the dairy-processing plant and to market the plant’s products. In July 2000, Earl Ransom, on behalf of EBWS, met with Britly’s president to discuss building the creamery.…In January 2001, EBWS and Britly entered into a contract requiring Britly to construct a creamery building for EBWS in exchange for $160,318.…The creamery was substantially completed by April 15, 2001, and EBWS moved in soon afterward. On June 5, 2001, EBWS notified Britly of alleged defects in construction. [EBWS continued to use the creamery pending the necessity to vacate it for three weeks when repairs were commenced].

On September 12, 2001, EBWS filed suit against Britly for damages resulting from defective design and construction.…

Following a three-day trial, the jury found Britly had breached the contract and its express warranty, and awarded EBWS: (1) $38,020 in direct damages, and (2) $35,711 in consequential damages.…

…The jury’s award to EBWS included compensation for both direct and consequential damages that EBWS claimed it would incur while the facility closed for repairs. Direct damages [i.e., compensatory damages] are for “losses that naturally and usually flow from the breach itself,” and it is not necessary that the parties actually considered these damages. [Citation]. In comparison, special or consequential damages “must pass the tests of causation, certainty and foreseeability, and, in addition, be reasonably supposed to have been in the contemplation of both parties at the time they made the contract.”…

The court ruled that EBWS could not recover for lost profits because it was not a going concern at the time the contract was entered into, and profits were too speculative. The court concluded, however, that EBWS could submit evidence of other business losses, including future payment for unused milk and staff wages.…

At trial, Huyffer, the CEO of EBWS, testified that during a repairs closure the creamery would be required to purchase milk from adjacent Rock Bottom Farm, even though it could not process this milk. She admitted that such a requirement was self-imposed as there was no written output contract between EBWS and the farm to buy milk. In addition, Huyffer testified that EBWS would pay its employees during the closure even though EBWS has no written contract to pay its employees when they are not working. The trial court allowed these elements of damages to be submitted to the jury, and the jury awarded EBWS consequential damages for unused milk and staff wages.

On appeal, Britly contends that because there is no contractual or legal obligation for EBWS to purchase milk or pay its employees, these are not foreseeable damages. EBWS counters that it is common knowledge that cows continue to produce milk, even if the processing plant is not working, and thus it is foreseeable that this loss would occur. We conclude that these damages are not the foreseeable result of Britly’s breach of the construction contract and reverse the award.…

[W]e conclude that…it is not reasonable to expect Britly to foresee that its failure to perform under the contract would result in this type of damages. While we are sympathetic to EBWS’s contention that the cows continue to produce milk, even when the plant is closed down, this fact alone is not enough to demonstrate that buying and dumping milk is a foreseeable result of Britly’s breach of the construction contract. Here, the milk was produced by a separate and distinct entity, Rock Bottom Farm, which sold the milk to EBWS.…

Similarly, EBWS maintained no employment agreements with its employees obligating it to pay wages during periods of closure for repairs, dips in market demand, or for any other reason. Any losses EBWS might suffer in the future because it chooses to pay its employees during a plant closure for repairs would be a voluntary expense and not in Britly’s contemplation at the time it entered the construction contract. It is not reasonable to expect Britly to foresee losses incurred as a result of agreements that are informal in nature and carry no legal obligation on EBWS to perform. “[P]arties are not presumed to know the condition of each other’s affairs nor to take into account contracts with a third party that is not communicated.” [Citation] While it is true that EBWS may have business reasons to pay its employees even without a contractual obligation, for example, to ensure employee loyalty, no evidence was introduced at trial by EBWS to support a sound rationale for such considerations. Under these circumstances, this business decision is beyond the scope of what Britly could have reasonably foreseen as damages for its breach of contract.…

In addition, the actual costs of the wages and milk are uncertain.…[T]he the milk and wages here are future expenses, for which no legal obligation was assumed by EBWS, and which are separate from the terms of the parties’ contract. We note that at the time of the construction contract EBWS had not yet begun to operate as a creamery and had no history of buying milk or paying employees. See [Citation] (explaining that profits for a new business are uncertain and speculative and not recoverable). Thus, both the cost of the milk and the number and amount of wages of future employees that EBWS might pay in the event of a plant closure for repairs are uncertain.

Award for consequential damages is reversed.…

CASE QUESTIONS

  1. Why, according to EBWS’s CEO, would EBWS be required to purchase milk from adjacent Rock Bottom Farm, even though it could not process this milk?
  2. Surely it is well known in Vermont dairy country that dairy farmers can’t simply stop milking cows when no processing plant is available to take the milk—the cows will soon stop producing. Why was EBWS then not entitled to those damages which it will certainly suffer when the creamery is down for repairs?
  3. Britly (the contractor) must have known EBWS had employees that would be idled when the creamery shut down for repairs. Why was it not liable for their lost wages?
  4. What could EBWS have done at the time of contracting to protect itself against the damages it would incur in the event the creamery suffered downtime due to faulty construction?