You are here

DO - ANALYSIS OF NON-VALUE-ADDED ACTIVITIES, OF THE RE-BALANCING LINE AND ANALYSIS OF RE-BALANCING OF WORK ACTIVITIES

19 January, 2016 - 17:08

According to Figure 1.9 and Figure 1.10 were analyzed the losses regarding NVAA and Insaturation. In fact were analyzed all 4 critical workstations (because they have the worst losses) and were identified 41 types of non-value-added activities (walking, waiting, turning, picking....) in the various sub-phases of the production process. In Table 1.4 is shown some examples of non-value-added activities analyzed (MUDA Analysis).

Some examples of standard tools used to analyze NVAA reduction (MUDA Analysis) for the 4 workstations are shown here below in Figure 1.10Figure 1.11 and Figure 1.12) job stratification (VAA - Value Added Activities; NVAA – Non-Value-Added Activities; LBL - Low Balancing Level; EAWS - European Assembly Work Sheet – Ergonomy); 2) Spaghetti Chart and 3) Kaizen Standard.

Table 1.4 MUDA Analysis - NVAA

Losses identified

Solution

Non-value-added activities identified

1

Pick picking list for sequencing

Complete hub sequencing

To pick

media/image10.png

2

Pick the box for sequencing

Complete hub sequencing

To pick

media/image10.png

3

Select sheets for the different model

Unification of the sheets from 3 to 1

To select

media/image11.png

4

Pick sheets for the different process

Unification of the sheets from 3 to 1

To pick

media/image10.png

5

Pick identification sheet

Unification of the sheets from 3 to 1

To pick

media/image10.png

6

Go to the printer to pick up sticker

Print sticker

To walk

media/image12.png

7

Pick identification hub label

Digital label with barcode

To pick

media/image10.png

8

Throw liner nameplate into the waste container

Print labels directly onto sheet unified

To trow

media/image13.png

9

Pick equipment for reading labels coupling

Automatic reading

To pick

media/image10.png

10

Combination of manual pallet

Automatic combination

To check

media/image14.png

11

Use of a single box

Enabling a second workstation

To walk

media/image12.png

12

Pick hub

Pick subgroup (hub+ damper

To pick

media/image10.png

13

Use of electrical equipment through keyboard

New air equipment without keyboard

To arrange

media/image15.png

14

Use of air equipment through keyboard

New air equipment without keyboard

To wait

media/image16.png

15

Transport empty box hub sequencing to put the full box

Complete hub sequencing

To transport

media/image17.png

16

Walk to the line side to pick damper

Complete hub sequencing

To walk

media/image12.png

17

Remove the small parts to pair with damper

Complete hub sequencing

To pick

media/image10.png

18

Transport empty box damper sequencing to put the full box

Complete damper sequencing

To transport

media/image17.png

19

Pick the hub and put on the line

Pick subgroup (hub+ damper)

To pick

media/image10.png

20

Select the work program for the next workstation

Select the work program

To select

media/image11.png

21

Press the feed button for the damper

Use a single workstation after the sequencing of the subgroup in order to press a button once

To push

media/image18.png

22

Wait for the translational motion of the pallet

Use a single workstation after the sequencing of the subgroup and match processing activities during the translation of the pallet

To wait

media/image16.png

 

   

media/image19.png
Figure 1.10 Details of the 4 workstations 
 
media/image20.png
Figure 1.11 Spaghetti Chart Example 
 
media/image21.png
Figure 1.12 Standard Kaizen analysis Example 
 

Figure 1.13 shows the initial scenario analyzed to identify problems and weaknesses.

media/image22.png
Figure 1.13 Details of the 4 workstations 
 

At this point was assumed the new flow of the complete damper (corner) = damper + complete hub sequencing according to the material matrix considering losses relating to handling (material matrix classification – see Figure 1.14). The material matrix classifies the commodities (number of drawings) in three main groups: A (bulky, multi-variations, expensive), B (normal) and C (small parts) and subgroups (a mixture of group A: bulky and multi-variations or bulky and expensive etc.). For each of these groups was filled out the flow matrix that defines the correct flow associated: JIS (and different levels), JIT (and different levels) and indirect (and different levels). After identifying the correct flow, in the JIS case, was built a prototype of the box (bin) to feed the line that would ensure the right number of parts to optimize logistic handling. However, the new box (bin) for this new mechanical subgroup must feed the line in a comfortable and ergonomic manner for the worker in the workstation, for this reason was simulated the solution before the realization of the box (bin) (see Figure 1.15).

media/image23.png
Figure 1.14 Material matrix example 
 
media/image24.png
Figure 1.15 Simulation of an ergonomic workstation 
 

At the end of the Muda analysis (NVAA analysis) were applied all the solutions found to have a lean process (the internal target is to achieve 25% of average NVAA losses) and was reorganized the line through a new line balancing level (rebalancing) to achieve 5% of the average line balancing losses (internal target). Another important aspect was the logistics flows analysis (see Figure 1.16) considering advanced warehouses ( Figure 1.17). The simulation scenario was defined using trucks from the Cassino plant warehouses that also feed other commodities to achieve high levels of saturation to minimize handling losses.

media/image25.png
Figure 1.16 Initial logistic flows 
 
media/image26.png
Figure 1.17 Logistic flows considering advanced warehouses 
 

At the end of the handling analysis (flow, stock level…) thanks to this new “lean” organization of material matrix was used the correct line feed from the Just In Sequence warehouse. It was reduced the internal warehouse (stock level), the space used for sequencing (square metres), the indirect manpower used to feed the sequencing area and we obtained zero forklifts on the shopfloor because we used the ro-ro (roll in - roll out) system. Figure 1.18 shows the final scenario in which we have 1 operator instead of 4 operators.

media/image27.png
Figure 1.18 Details of the final workstation